Newport Beach & Costa Mesa · Pipeline Report

Coastal OC Development Watch

Every significant project under construction, approved, or in review across Newport Beach and Costa Mesa, with the goals behind each one and what residents actually said at the hearings. Ordered by when each is expected to finish, so the top of each list is what you will see first.

Last updated October 23, 2026 Next scheduled review: January 2027, after both cities file year-end housing reports and the November 3 election results are certified. Compiled from city council and planning commission records, CEQA filings, Coastal Commission reports, and local press. Sources on every card.
How to read this page
Under construction
Permits pulled and crews on site. The finish date is the builder's or the city's published target.
Approved
Fully entitled by the city. Can still be delayed by financing, lawsuits, or the builder's own timing.
In review
An application is on file and moving through environmental review or hearings. Details can change.
Stalled or dead
Approved but idle for years, withdrawn, rescinded, or replaced by a different use.

On dates: Stated means the developer or city has published that target. Estimated means no date has been published, and the range is our read from the approval date and typical build times for that product type. Neither is a promise. If a project matters to a decision you are making, call us and we will pull the current file.

City one

Newport Beach

4,845homes the state requires the city to plan for, 2021 to 2029
8,174homes the city zoned for across five focus areas in 2024
372homes actually permitted since 2021, per the city's 2025 annual report
Nov 3Measure H vote that would cut the five-area cap to 2,900 income-restricted units
Why housing is on the ballot

In 2024 the city council rezoned five areas (the Airport Area, Newport Center, West Newport Mesa, Dover-Westcliff, and Coyote Canyon) for up to 8,174 new homes, well above the 4,845 the state requires. Planners built in the cushion because most rezoned parcels never redevelop. Council did this without the public vote that Newport's 2000 Greenlight law normally requires, on the position that state housing law overrides it. A judge agreed in June 2025; that ruling is on appeal, and a second lawsuit filed this month asks the court to freeze every project that relies on the new zoning.

Measure H, on the November 3 ballot, would cut the five-area cap to 2,900 units, all income-restricted, with no market-rate homes. The state housing department has warned the city in writing that passage could cost Newport its certified housing plan, which opens the door to builder's-remedy projects and monthly fines.

The case for H
  • 8,174 units is far more than the state asked for
  • Traffic, height, and school capacity were never studied at that scale
  • Residents lost the vote Greenlight promised them
The case against H
  • Risks decertification, builder's remedy, and state penalties
  • Removing market-rate units removes what funds the affordable ones
  • Its largest funder is an airport-area apartment developer with projects already approved

What it means for the projects below: anything with an application already on file keeps today's rules whichever way the vote goes. Projects that have not yet filed could face new caps.

Fall 2026Stated · city and Army Corps target
Under construction

Lower Newport Bay Dredging

Newport Harbor, staged from Marina Park · City of Newport Beach with the U.S. Army Corps of Engineers

Roughly 900,000 cubic yards of sediment removed from the lower harbor, the largest dredge the harbor has seen and, per the city, the last major one. Work began November 2025 on a 10-to-12-month schedule. About a fifth of the material tested as contaminated and is being barged to the Port of Long Beach for pier fill after a plan to bury it under the harbor floor was abandoned following a Coastkeeper lawsuit.

Project goals

Restore navigable depths for the channels, mooring fields, and marinas, and reduce future dredging needs for decades.

What supporters say
  • Decades-overdue for boaters and marina operators
  • Settles the contaminated-sediment question without burying it in the bay
What neighbors raised
  • Months of barge traffic and staging at Marina Park
  • Coastkeeper's original objection to the in-harbor disposal plan

Sources: City of Newport Beach project launch (Nov 2025) · OC Coastkeeper · Newport Beach Independent

Late 2026Stated summer 2026 target · completion not yet confirmed
Under construction

Lido House Hotel Expansion

3300 Newport Blvd, Lido Village · R.D. Olson

Five additional cottages (about 9,500 square feet), the Cotton Pavilion event space, added meeting rooms, and a private dining room. Built in three phases since March 2025 while the hotel stays open.

Project goals

Add event and group capacity to the Lido Village hotel without changing its scale or the former City Hall site's character.

What supporters say
  • Keeps Lido Village's anchor hotel competitive
  • Low-rise cottages match the existing design
What neighbors raised
  • Event noise and valet traffic on Via Lido and 32nd Street

Sources: R.D. Olson Construction announcement (Mar 2025) · City of Newport Beach permit records

2027Estimated · under construction per the city's 2025 report; opening date not published
Under construction

2510 & 2530 West Coast Highway

Mariners' Mile · private owner

Two mixed-use buildings with 36 apartments (three set aside for very-low-income households) over ground-floor commercial. Uchi, the Austin-born sushi restaurant, is approved for the 2510 building.

Project goals

The first new housing built on Mariners' Mile under the city's 2024 rezoning, pairing small-scale apartments with destination dining on the harbor side of PCH.

What supporters say
  • Modest height, fits the existing commercial strip
  • Brings a nationally known restaurant to the Mile
What neighbors raised
  • Parking on an already tight stretch of PCH
  • Sets the precedent for larger Mariners' Mile projects

Sources: City of Newport Beach 2025 Housing Element Annual Progress Report · Planning Commission (Dec 2024)

2027Estimated · under construction since 2025; sales timing not announced
Under construction

Residences at 1401 Quail

1401 Quail St, Airport Area · Intracorp Homes

67 for-sale condominiums over a 146-space garage, replacing an office building. Eight units are income-restricted (six very-low, two low). Council approved it in April 2024 and it is one of the few airport-area projects with a crane up.

Project goals

Ownership housing, not rentals, in a district that has been almost entirely office since the 1970s.

What supporters say
  • For-sale product is rare in the Airport Area pipeline
  • Replaces an aging office building on a site already served by roads and utilities
What neighbors raised
  • John Wayne Airport noise for ground-level units
  • Few neighbors to object; the surrounding blocks are commercial

Sources: City of Newport Beach 2025 Annual Progress Report · Planning Commission (Dec 2023), City Council (Apr 2024)

Early 2028Stated · developer target
Under construction

Villas Fashion Island Expansion

800 San Clemente Dr, Newport Center · Irvine Company

184 apartments in a five-story building over a two-level, 287-space garage, on 2.2 acres where an 842-space parking structure came down in December 2025. Brings the Villas to 708 homes. Approved at staff level under Irvine Company's Newport Center plan, so it never went to a public hearing.

Project goals

Convert a parking structure into housing next to Fashion Island, using the 1,500 units council allocated to Irvine Company's Newport Center holdings in 2025.

What supporters say
  • City staff: a site that was serving no real purpose becomes housing
  • Walkable to Fashion Island jobs and retail
What neighbors raised
  • No public hearing for a 184-unit building
  • Fashion Island parking during construction and the holidays

Sources: City of Newport Beach · CEQAnet PA2025-0131

2028 to 2029Stated · construction 2027, completion 2028 to 2029 per buyer Shea Homes
Approved

Park Palm at Uptown Newport

Jamboree Rd at Birch St, Airport Area · Shea Homes (site bought from Shopoff, Aug 2026)

23 for-sale townhomes on the last one-acre pad of Uptown Newport's first phase, next to One Uptown Newport (458 apartments) and the Parkhouse condos. Part of a 25-acre master plan approved in 2013 for 1,244 homes; roughly 750 units remain for a second phase on the former semiconductor plant next door, with no current schedule.

Project goals

Finish Phase 1 of the Airport Area's first true residential neighborhood with ownership product beside the existing park.

What supporters say
  • Small, for-sale, and inside an already-approved plan
  • Shea has delivered comparable townhomes in Irvine and Tustin
What neighbors raised
  • Uptown's promised retail is still on hold
  • Airport noise disclosures apply to every unit

Sources: City of Newport Beach Uptown Newport approvals (2013) · Orange County Recorder (Aug 2026 sale)

2028 to 2029Estimated · approved April 2026; no schedule published
Approved

Residences at 1500 Quail

1500 Quail St, Airport Area · Lincoln Property Company with TPG Angelo Gordon

100 for-sale townhomes, three and four bedrooms, roughly 1,590 to 1,880 square feet with two-car garages, in 24 three-story buildings on 4.8 acres. Replaces an 86,000-square-foot office tower. The Planning Commission approved it unanimously in April 2026 after the developer dropped an earlier 474-apartment version. No income-restricted units; staff relied on the citywide housing buffer.

Project goals

Entry-level ownership for Newport Beach, priced below the coastal market by building on office land near the airport.

What supporters say
  • Attainable for-sale homes with garages, a product the city has almost none of
  • Lower height and density than the apartment version it replaced
What neighbors raised
  • Zero affordable units in a project that counts toward the housing plan
  • Airport overflight noise for a family-oriented product

Sources: Planning Commission (Apr 2026) · Orange County Business Journal (Apr 2026)

2029Estimated · final approval August 2026; office buildings already demolished
Approved

1300 Dove (Redstone Campus)

1200 and 1300 Dove St and 4041 MacArthur Blvd, Airport Area · Lincoln Property Company

132 for-sale homes in 36 small buildings on 6.5 acres, two to four bedrooms from about 1,250 to 2,560 square feet, with seven very-low-income units, 40 guest parking spaces, and a 9,000-square-foot public walkway along MacArthur. Two 173,000-square-foot office buildings have been cleared. Council reduced the park fee from about $6.5 million to about $1 million as part of the approval.

Project goals

A second for-sale neighborhood in the Dove Street corridor, where five office-to-housing conversions now total about 815 units.

What supporters say
  • Ownership housing at a scale that could create an actual neighborhood
  • Public walkway and street improvements on MacArthur
What neighbors raised
  • A $5.5 million park-fee reduction with no park on site
  • Seven affordable units out of 132

Sources: Orange County Business Journal (Aug 2026) · CEQAnet Notice of Determination (Aug 27, 2026)

2028 to 2029Estimated · approved September 2025; no schedule published
Approved

Monrovia Townhomes

1580 to 1598 Monrovia Ave and 865 to 899 W. 16th St, West Newport Mesa · Intracorp Homes

89 for-sale homes on 4.3 acres: four single-family houses, 34 duplex units, and 51 townhomes. Replaces light-industrial buildings in the West Newport Mesa focus area between Hoag and the Costa Mesa line.

Project goals

Begin the industrial-to-residential transition the city planned for West Newport Mesa, with ownership product near Hoag Hospital.

What supporters say
  • Mixed product types rather than a single townhome block
  • Walkable to Hoag, Newport Heights schools, and the Superior Avenue bridge to the beach
What neighbors raised
  • Cut-through traffic on 16th and Monrovia
  • Displaces small businesses and the artisan shops along 16th

Sources: Planning Commission Resolution 2025-20 · CEQAnet Notice of Exemption (Sept 19, 2025)

2028 to 2029Estimated · both cleared the Planning Commission in 2026; final council action not confirmed
Approved at Planning Commission

Dover Shores Townhomes: 601 Dover and Westcliff at Dover

601 Dover Dr (Shea Homes) and 1501 16th St (D.R. Horton), Dover-Westcliff

Two separate projects, 63 homes total, both replacing vacant medical buildings at the foot of Dover Shores. 601 Dover: 33 three-story townhomes in seven buildings, 38 feet tall, with access from Cliff Drive; Planning Commission approved 4-1 in February 2026. Westcliff at Dover: 30 three-story townhomes of 2,090 to 2,400 square feet on the former Newport Bay Hospital site; Planning Commission recommended approval 4-2 in June 2026 after requiring balcony removals and landscape buffers facing the Environmental Nature Center.

Project goals

Family-sized ownership homes in the Dover-Westcliff focus area on sites that have been empty for years.

What supporters say
  • Vacant, blighted buildings replaced with housing near Mariners and Ensign schools
  • Low unit counts compared with the rest of the pipeline
What neighbors raised
  • Illegal U-turns and school drop-off congestion at Dover and Cliff
  • Privacy and noise for the Environmental Nature Center's preschool
  • Three-story massing next to single-story Westcliff homes

Sources: Planning Commission hearings (Feb 5 and June 18, 2026) · CEQAnet 2026060960

2029 to 2030Estimated · council approved November 2025; site plan and traffic study still ahead
Approved

MacArthur Court

4665 to 4695 MacArthur Ct and 4770 Campus Dr, Airport Area · Irvine Company

700 market-rate apartments in two five-story buildings plus 10,000 square feet of retail and restaurant space on about 17 acres. Up to 49 income-restricted units are to be built off-site by early 2029 or paid for in lieu. The development agreement includes roughly $3.3 million toward MacArthur Boulevard improvements and a per-unit fee for permits pulled after mid-2028.

Project goals

The largest single apartment project in the Airport Area, replacing office buildings on land Irvine Company already owns.

What supporters say
  • Housing where the jobs are, with a proven owner-operator
  • Retail and street improvements along MacArthur
What neighbors raised
  • Eastbluff HOA: 7% affordable is too low and should be built on site, up front
  • 700 units of traffic onto MacArthur and Jamboree

Sources: City Council Ordinance 2025-36 · CEQAnet Notice of Exemption (Dec 10, 2025)

2029 and laterEstimated · all five approved between 2021 and 2024; none confirmed under construction
Approved

Picerne Group Airport-Area Portfolio

1300 Bristol · 1400 Bristol · 1600 Dove · 4400 Von Karman · Newport Airport Village (Campus Dr at MacArthur) · The Picerne Group

Five approved rental projects totaling roughly 1,450 apartments: 193 units at 1300 Bristol, 229 at 1400 Bristol, 249 to 282 at 1600 Dove, 312 at 4400 Von Karman with a one-acre public park, and 444 at Newport Airport Village. Combined, about 160 are income-restricted. Several are in plan check; none has a confirmed groundbreaking. Picerne is also the sole million-dollar funder of Measure H, which would cap future airport-area housing after these projects are counted.

Project goals

Replace 1970s office buildings with podium apartments and, at Von Karman, the Airport Area's first public park.

What supporters say
  • Carries the bulk of the city's near-term housing count
  • Koll Center park and garage improvements come with 4400 Von Karman
What neighbors raised
  • Approved for years with nothing built; neighboring office owner Olen Properties is in litigation over the Von Karman project
  • The developer funding a measure that limits competitors

Sources: City of Newport Beach 2025 Annual Progress Report · Orange County Business Journal (Jan and Mar 2026) · LAist Measure H guide

2030 and laterEstimated · appeal denied April 2026; theater lease ends June 2027; no construction schedule published
Approved

300 Newport Center (Big Newport Theater Site)

210 and 300 Newport Center Dr, Fashion Island · Related California

Two 22-story, 270-foot towers with 150 for-sale condominiums of two to four bedrooms, roughly 2,100 to 6,400 square feet, plus a small café and for-sale home offices, on the 4.2-acre site of the Regal Edwards Big Newport theater and a fitness club. No income-restricted units. The Planning Commission approved it in March 2026 and council unanimously denied an appeal in April. The Edwards family has said the theater's lease will not be extended past June 2027.

Project goals

Newport Center's first new high-rise residences in a generation, aimed at the downsizing buyer leaving a large coastal home.

What supporters say
  • Council: in character with the existing towers and served by existing infrastructure
  • For-sale luxury product that funds affordable units elsewhere through fees
What neighbors raised
  • Loss of the 57-year-old Big Newport, a regional landmark
  • Zero affordable units in a 150-home project
  • Calls for an events center or more public process on high-rise height

Sources: Planning Commission Resolution PC2026-004 · City Council appeal hearing (Apr 28, 2026) · Orange County Business Journal (Mar and May 2026)

2030 and laterEstimated · development agreement approved October 13, 2026; no site plans yet; five-year vesting
Approved

Fairway Three at Newport Beach Country Club

1600 E. Coast Hwy, Newport Center · Eagle Four Partners

78 luxury for-sale homes on 2.2 acres at the northeast edge of the 128-acre club, overlooking the third hole. Council unanimously approved the development agreement on October 13, 2026, with second reading October 27. The agreement locks in rules for five years and sets a fee of about $128,000 per home toward parks and public benefits. A northwest portion of the course is flagged for possible future housing.

Project goals

Golf-frontage homes a short walk from Fashion Island, on land the club says it no longer needs for play.

What supporters say
  • Low density on private land with no neighbors displaced
  • About $10 million in park and public-benefit fees
What neighbors raised
  • No guaranteed progress on the city's affordable-housing obligations
  • Opens the door to more course acreage being converted later

Sources: City Council agenda and development agreement (Oct 13, 2026) · Planning Commission (Sept 2026)

Not setIn environmental review since 2023; needs Coastal Commission approval after the city
In review

Newport Village on Mariners' Mile

2000 to 2244 W. Coast Hwy, both sides of PCH · MX3 Ventures

198 homes on 9.4 acres of the former Ardell properties: 181 apartments (nine very-low-income) on the inland side and 17 condominiums on the waterfront, with about 63,000 square feet of office, retail, and restaurant space, a public plaza, roughly 950 feet of new waterfront boardwalk, and 848 parking spaces. Base height is 35 feet, with density-bonus waivers that could push portions toward 50. The city deemed the application complete in 2025; the draft environmental report has not been released.

Project goals

Remake the largest undeveloped stretch of Mariners' Mile with public harbor access that does not exist today.

What supporters say
  • Public boardwalk and plaza on a waterfront that is currently fenced boatyards
  • Replaces vacant lots that have sat empty for a decade
What neighbors raised
  • Cliff Drive and Kings Road residents: bluff-top views and property values
  • Protect Mariners' Mile: height, PCH traffic, and the scale of a 9-acre project

Sources: City of Newport Beach project page · 2025 Annual Progress Report · Newport Beach Independent

Fall 2027Stated · earliest public opening per the Mountains Recreation and Conservation Authority
Approved as open space

Randall Preserve (formerly Banning Ranch)

West Newport, bordering Costa Mesa's Westside · Mountains Recreation and Conservation Authority, with the Coastal Corridor Alliance

About 387 acres of coastal mesa and lowlands that were the subject of a 20-year fight over 1,375 proposed homes. Purchased for permanent open space in 2022. Oil operations are being consolidated onto a 14-acre inholding and remediated; the main public entrance is planned at West 17th Street in Costa Mesa. A state grant in February 2026 funds a wetland-restoration study for about 130 lowland acres. This is the single most common question we get, so: no homes are coming here.

Project goals

Public trails, habitat restoration, and eventually a restored tidal wetland on the last large undeveloped coastal parcel in Orange County.

What supporters say
  • Permanent open space next to Newport Shores, West Newport, and the Westside
  • Adds a major park to the park-poorest part of both cities
What neighbors raised
  • Whether dogs and bikes will be allowed near 18 sensitive species
  • Parking and traffic at the 17th Street entrance

Sources: California State Coastal Conservancy (Feb 2026) · LAist (June 2025) · MRCA draft access plan

Also in the Newport Beach pipeline
ProjectWhereWhatStatusExpected
Park Newport expansion1 Park Newport, Jamboree at San Joaquin HillsUp to 366 apartments (15 low-income) on 6 acres of the existing complex; Prado GroupIn review (filed Jan 2025)Not set
Block 100, Newport Center100 to 190 Newport Center DrAbout 600 rental units in four five-story buildings replacing office; Irvine CompanyIn review (preliminary application)Not set
Residences at Newport Center150 Newport Center Dr (former car wash)28 condos, four storiesApproved 2021; in plan checkEst. 2028
Back Bay Landing / Bayside Village Marina300 E. Coast HwySeawall replacement, 67 added slips, dredging, bike-path easements; the 2014 mixed-use plan remains stalledIn review (supplemental EIR, Oct 2025)Not set
OC San Bay Bridge Pump Station250 E. Coast Hwy$87 million sewer station and force mains; intermittent PCH lane closuresUnder construction2029
Lower Castaways100 Dover DrMarine interpretive center, kayak launch, café, trail link to Upper Castaways; aquatics center shifted to Mariners' ParkIn planning (RFP stage)Not set
Newport Crossings1660 Dove St, Koll Center350 apartments (78 low-income), 0.5-acre park; approved 2019, site listed for saleStalledNot set
Ritz-Carlton Residences900 Newport Center Dr (VEA campus)Up to 159 hotel-branded condos in a 22-story tower; hotel wing demolished 2023, no groundbreakingStalledNot set
Coyote Canyon20662 Newport Coast Dr (closed landfill)Zoned for up to 1,530 units; no housing application on file; a landfill-gas energy plant is in reviewNo projectNot set
Snug Harbor Surf ParkNewport Beach Golf Course, 3100 Irvine AveApproved Oct 2025, rescinded Jan 2026 after a 6,100-signature referendum; the course's 700-plus-unit housing overlay has no applicationDeadn/a
New police headquartersCivic Center or Dove St siteRoughly $150 to $230 million; council split over using the Civic Center sculpture gardenUndecidedNot set
Hoag Newport Beach master plan1 Hoag DrUp to 225,000 sf reallocated between campuses, new Neuroscience CenterIn review (refiled Oct 2024)Not set
Witte Hall998 Avocado Ave, Central Library299-seat lecture hallOpened July 2026Done

City two

Costa Mesa

11,760homes the state requires the city to plan for, 2021 to 2029
~550homes permitted so far, under 5% of the goal, per state figures reported in October 2026
2,300homes in the plan council adopted for the state-owned Fairview Developmental Center
Oct 20council hearing on a citywide rezoning that resets height and density along every major corridor
The rezoning most residents have not heard about

Costa Mesa's state housing target is more than double Newport's, and the city has been out of compliance since August 2025 because the rezoning it promised was never finished. The California Attorney General sued in July 2026. The city's response is a package called Neighborhoods Where We All Belong, built on the Measure K corridors voters approved in 2022. It went to council on October 20, 2026 after a 3-1 Planning Commission recommendation, with a second reading expected in November and a state deadline of December.

If adopted as proposed, it rewrites the zoning for more than a thousand properties, repeals the Westside and SoBECA urban plans, removes most parking minimums on housing sites, moves many approvals to staff-level review, and overrides the airport commission's objection to housing under the John Wayne flight path. The environmental report counts capacity for about 22,000 homes through 2056.

CorridorProposed densityHeight
Westside (19 West, Mesa West Bluffs)20 to 30 units/acre60 ft
Newport Blvd and Harbor Blvd30 units/acre60 ft
SoBECA40 units/acre60 ft
North Costa Mesa60 units/acre72 ft
Select North CM housing sitesUp to 90 units/acre108 ft
The case for
  • Ends the state lawsuit and restores local control over approvals
  • Housing near jobs, transit, and South Coast Metro
  • Workforce housing for teachers, service workers, and seniors
The case against
  • No traffic or fiscal study at a 51,000-resident scale
  • 31 significant environmental impacts the city would accept as unavoidable
  • Fewer public hearings, no new parks, mostly rentals
2026Stated summer 2026 opening · occupancy not yet confirmed
Under construction

Avon River Apartments

1400 Bristol St (former Travelodge) · American Family Housing, with Costa Mesa, Newport Beach, and the County

A 120-room motel converted to 76 permanent supportive studios and one-bedrooms through the state's Homekey program. Funded at about $45 million, including $3 million from Newport Beach in exchange for 12 referral slots. Broke ground August 2025; the county opened the waitlist in April 2026.

Project goals

Housing with on-site services for people exiting homelessness, replacing a motel the city had long flagged for police calls.

What supporters say
  • Converts a problem property with mostly state money
  • Two cities sharing one project
What neighbors raised
  • Concentration of supportive housing along Bristol and Harbor
  • Service and security staffing once the state grant runs out

Sources: Orange County Housing Authority notice (Apr 2026) · Assemblymember's office (Aug 2025) · American Family Housing

2027Estimated · height variance approved September 2026; opening date not announced
Approved

DICK'S House of Sport, Harbor at Wilson

2200 Harbor Blvd, Gray Plaza · DICK'S Sporting Goods

A roughly 94,000-square-foot experiential store with a climbing wall, golf simulators, and batting cages, the chain's flagship format. The Planning Commission approved a 50-foot height variance 7-0 in September 2026. The same night it approved PadelUp, five outdoor padel courts at 2045 Harbor.

Project goals

Re-anchor a tired Harbor Boulevard center with a regional draw instead of another big-box turnover.

What supporters say
  • Sales tax and foot traffic on the Harbor corridor
  • No housing displaced; reuses an existing retail pad
What neighbors raised
  • Weekend traffic at Harbor and Wilson
  • 50-foot height on a corridor the rezoning sets at 60

Sources: Planning Commission (Sept 14, 2026)

2027 to 2028Stated · construction 2026, model homes 2027 per the builder
Breaking ground

Bear Street Residential (former Trinity Broadcasting campus)

3150 Bear St, between the 405 and 73 · Meritage Homes

142 for-sale homes on the six-acre former TBN headquarters: 122 four-story stacked-flat townhomes of roughly 1,000 to 2,400 square feet and 20 detached two-story houses. Seven units are very-low-income. Council rezoned the site in August 2025, Meritage closed on it for $44.5 million in November, demolition is done, and the final tract map went to council on October 6, 2026. Pricing has not been released.

Project goals

The one true new-construction, for-sale community either city will have open for sale in 2027.

What supporters say
  • Ownership housing from a national builder with a track record in Costa Mesa (17 West)
  • Freeway-adjacent site with no residential neighbors to disrupt
What neighbors raised
  • Freeway noise and air quality for ground-floor units
  • Seven affordable units out of 142

Sources: CEQAnet 2025050135 · City Council (Aug 5, 2025 and Oct 6, 2026)

2027 to 2028Stated fall 2027 completion · construction start not yet confirmed
Approved and funded

Costa Mesa Senior Apartments at the Senior Center

695 W. 19th St at Pomona Ave, Westside · Jamboree Housing on a city ground lease

Four stories, 70 apartments for residents 55 and older on part of the Senior Center parking lot. Half are reserved for seniors exiting homelessness; the rest are income-restricted, with a preference for Costa Mesa residents. The city leased the land for $1 a year and loaned $3.25 million; the state awarded tax credits in June 2026. Total cost is about $59 million.

Project goals

Senior housing next to the services seniors already use, on land the city already owns.

What supporters say
  • Fully financed, which most affordable proposals never reach
  • Parking study found no impact on Senior Center users
What neighbors raised
  • Four stories on a block of one- and two-story buildings
  • Construction timeline keeps slipping

Sources: City Council (Mar 2025, Mar 2026) · Orange County Board of Supervisors (Mar 2026) · Jamboree Housing

2028Estimated · approved September 28, 2026; builder cites 18 to 24 months of construction
Approved

Eira, 396 East 21st Street

Eastside, between Tustin Ave and E. 21st · private developer

21 detached two-story houses in a Nordic-farmhouse style on 1.5 acres that was a 28-space mobile home park. One house is a very-low-income for-sale unit, which earned the project ten density-bonus waivers. 60 parking spaces. The Planning Commission approved it in September 2026.

Project goals

Detached, single-family new construction on the Eastside, which otherwise sees only one-off custom rebuilds.

What supporters say
  • Missing-middle product on a site that has sat vacant
  • Detached homes rather than stacked units next to single-family blocks
What neighbors raised
  • Traffic near Kaiser and Woodland elementary schools and the Boys and Girls Club
  • Loss of the mobile home park's de facto affordability
  • Street parking overflow onto 21st

Sources: Planning Commission (Sept 28, 2026)

2028Estimated · final approval August 2025; no timeline or pricing released
Approved

Victoria Place

Newport Blvd at Victoria St (220 to 236 Victoria), Eastside edge · WMC LLC

40 for-sale condominiums on 1.8 acres: 36 duplex-style units plus four detached, each about 2,750 square feet with a ground-floor office of roughly 425 square feet. No income-restricted units. The Planning Commission denied it; council approved it on appeal in July 2025.

Project goals

Live/work ownership for small-business owners and remote professionals on the Newport Boulevard corridor.

What supporters say
  • Large for-sale units, rare in a pipeline dominated by rentals
  • Ground-floor offices keep a commercial feel on the corridor
What neighbors raised
  • Converting commercial corridor land to housing
  • Planning Commission's original denial over design and parking

Sources: City Council (July 15 and Aug 5, 2025) · CEQAnet 2025031168

2027 to 2029Estimated · all three entitled; 960 W. 16th furthest along
Approved

Westside Live/Work Projects

960 W. 16th St (Intracorp, 38 units) · 1540 Superior Ave (9 units) · 1711 to 1719 Pomona Ave (8 units)

Three small ownership projects, 55 homes total, continuing the Westside's shift from light industrial to live/work townhomes that Citivest's Pacific Avenue and Meritage's 17 West began. 960 W. 16th is the largest at 38 units. The Pomona project received an 18-month extension in March 2026 after utility-undergrounding delays.

Project goals

Infill ownership product on the blocks closest to Randall Preserve and the Newport Beach line.

What supporters say
  • Small-scale, for-sale, and already entitled under the Westside urban plans
  • Walkable to 17th Street and the future preserve entrance
What neighbors raised
  • Piecemeal loss of industrial and artist space
  • The proposed rezoning would allow 60-foot buildings on these same blocks

Sources: CEQAnet 2025020484 and 2023100322 · City Council (Mar 9, 2026)

2028Estimated · $16 million in bonds priced November 2026; construction to follow
Approved and funded

Fire Station No. 2 Replacement

800 Baker St, Mesa Verde edge · City of Costa Mesa

A 9,445-square-foot LEED Gold station replacing the 1966 building. The construction contract is $14.8 million; total cost grew from about $12 million to about $16 million, and council is issuing lease-revenue bonds to cover it.

Project goals

Modern apparatus bays and crew quarters for the station that covers Mesa Verde, South Coast Metro, and the 405 corridor.

What supporters say
  • 60-year-old station no longer fits current engines
  • Response-time coverage for the north side as it densifies
What neighbors raised
  • A one-third cost increase before ground is broken
  • Borrowing for a single station while the facilities plan flags others

Sources: City Council (Oct 20, 2026 bond hearing) · CEQAnet 2024100815

2028 to 2031Stated · first residents 2028 per the developer, phased over about three years; no groundbreaking yet
Approved

One Metro West

1683 Sunflower Ave, north of the 405 · Rose Equities with Garden Communities

957 apartments (trimmed from 1,057 in May 2026) in three six- and seven-story buildings on a 15-acre former warehouse site, with 106 income-restricted units, a 42,000-square-foot resident co-working and amenity building, 6,000 square feet of retail, a 1.7-acre public park, three pools including one on a roof, and 1,766 parking spaces. Approved in 2021 with a $68 million community-benefits package; targets in 2022 and 2025 came and went.

Project goals

The largest housing project in Costa Mesa history, designed around work-from-home floor plans and a public park in a district that has none.

What supporters say
  • 106 affordable units and a real park without public money
  • City estimates a $350 million economic impact
What neighbors raised
  • Sunflower and 405 traffic at full build-out
  • Approved without the public vote Measure Y once required
  • Five years approved with nothing built

Sources: City of Costa Mesa project page · CEQAnet Notice of Determination (May 29, 2026)

Not setParcel acquired August 2026; plans to be announced
In planning

Project SoBECA (The LAB and The CAMP district)

Bristol St at Baker, SoBECA · LAB Holding (Sadeghi family)

The family that built The LAB and The CAMP bought the 18,000-square-foot Pep Boys parcel on Bristol for $10.5 million in August 2026, the largest piece of the district they did not already own, and say plans will be unveiled as Project SoBECA. More than 20 small businesses opened in the district in 2026 and the Anti-Mall has been under renovation since 2025. The citywide rezoning would repeal the 2006 SoBECA plan and allow 40 units per acre at 60 feet here.

Project goals

Keep SoBECA independently owned and extend the LAB/CAMP model to the one corner that was a tire shop.

What supporters say
  • Local owners rather than an institutional buyer
  • Continuity for a district that defines Costa Mesa's identity
What neighbors raised
  • What 60-foot zoning does to a low-slung arts district over time
  • Rent pressure on the small tenants the district is known for

Sources: Orange County Business Journal (Aug 2026) · The CAMP journal (2026)

Not setEnvironmental review circulated spring and summer 2026; not yet before council
In review

Fairview Park Master Plan Update

208 acres on the Westside bluffs above the Santa Ana River · City of Costa Mesa

The first comprehensive update to the plan for Costa Mesa's largest park. The environmental document circulated in May 2026 and again in August after comments; a steering committee reviewed it in October. Separately, about 1,000 feet of trail was converted to decomposed granite and the model-glider field's agreement has expired, with residents asking that it be relocated.

Project goals

Balance habitat protection, trails, and active uses on land that borders Randall Preserve and the river.

What supporters say
  • A single plan for the park and the preserve next door
  • Protects vernal pools and native habitat
What neighbors raised
  • Fly-field users and dog walkers losing access
  • Parking and traffic in the Mesa Verde and Westside streets that feed the park

Sources: CEQAnet 2026041370 · City of Costa Mesa Parks and Community Services (Oct 2026)

2030sEstimated · specific plan adopted September 2026; the state must still select a master developer
Plan approved

Fairview Developmental Center

2501 Harbor Blvd, 110 state-owned acres · State of California, with a master developer to be chosen

The closed state hospital campus is the largest development site in either city. Council unanimously adopted a specific plan on September 15, 2026 allowing up to 2,300 homes, 920 of them income-restricted including 200 permanent supportive units, with 25 acres of open space including lighted fields and up to 35,000 square feet of neighborhood retail. No road will cut through the Costa Mesa Country Club. Staff said 3,450 units would be financially feasible and the state supports up to 4,000; council held at 2,300. Site preparation, including about $30 million of hazardous-materials cleanup, is estimated near $300 million.

Project goals

A new neighborhood on Harbor Boulevard that carries a fifth of the city's state housing obligation on land that costs the city nothing.

What supporters say
  • Forty-plus speakers: housing for teachers, seniors, young families, and residents with disabilities
  • Lighted fields and 25 acres of open space in a park-poor part of town
  • Avoids state penalties and keeps the housing plan whole
What neighbors raised
  • Harbor and Merrimac traffic and emergency response times
  • Earlier concepts were closer to 1,500 units
  • Hazmat cleanup, air quality, and trust in the state as landowner

Sources: City of Costa Mesa FDC Specific Plan · CEQAnet 2025101405 · Voice of OC (Sept 2026)

Also in the Costa Mesa pipeline
ProjectWhereWhatStatusExpected
Mesa Vista Apartments Phase II2274 Newport Blvd47 added supportive and senior units (86 total); Community Development Partners and Mercy HouseUnder construction (closed Feb 2025)2026 to 2027
Adams Avenue cycle tracksAdams Ave, Harbor to FairviewProtected two-way bike lanesUnder construction since Feb 20262026
Fairview Road NorthFairview Rd north of Fair DrFederally funded street and bike improvementsFunded; construction must start by early 20272027 to 2028
Fair Drive For AllFair Dr, OC Fairgrounds frontageComplete-streets redesign; design contract awarded Oct 2026In designNot set
OC Fair and Event Center master plan88 Fair DrEight phases through 2032: admin expansion, Century Barn, agriculture education center, exhibit halls, amphitheatre upgradesPhase 1 approved 2023Through 2032
2195 Pacific AveWestside10-unit small-lot subdivisionIn reviewNot set
2000 Harbor BlvdHarbor at Hamilton, next to 420 CentralVacant commercial parcel added to the housing inventory March 2026; developer talks reportedPre-applicationNot set
Sakioka Lot 2Anton Blvd area, North Costa MesaThe Sakioka family's last undeveloped parcel; rezoning sets a 120-foot height limitNo applicationNot set
Mesa Motel SRO2205 Harbor Blvd47 single-room units for very-low-income veterans and seniors; approved Apr 2025, property now listed for saleStalledNot set
Hive Live3333 Susan St1,050-unit proposal withdrawn; campus sold Oct 2025 and fully leased to Anduril IndustriesDeadn/a
South Coast Plaza parcelsSunflower Ave and Bristol StC.J. Segerstrom & Sons withdrew 14 parcels from the housing inventory in March 2026; no redevelopment proposedNo projectn/a
Related Bristol and The Village Santa AnaSouth Bristol St, across the line in Santa AnaTwo large mixed-use projects (apartments, hotel, senior living; 1,583 units) directly across from South Coast PlazaApproved; Santa AnaPhase 1 about 2030

New construction

For-sale communities to watch

Almost everything in the two pipelines is rental. These are the projects that will actually come to market as new-construction homes you can own, in the order pricing is likely to be released. None has published prices yet. Tell us which ones interest you and we will send the release the day it lands, along with the resale alternatives in the same pocket.

Bear Street, Costa Mesa142 townhomes and detached homes · MeritageModels 2027. First to market.
Residences at 1401 Quail, Newport Beach67 condos · IntracorpUnder construction; sales timing not announced.
Eira, 396 E. 21st, Costa Mesa21 detached homesApproved Sept 2026; est. 2028.
Park Palm at Uptown Newport23 townhomes · Shea HomesConstruction 2027; completion 2028 to 2029.
Victoria Place, Costa Mesa40 live/work condosApproved; est. 2028.
Residences at 1500 Quail, Newport Beach100 townhomes · Lincoln PropertyApproved Apr 2026; est. 2028 to 2029.
Monrovia Townhomes, Newport Beach89 homes · IntracorpApproved Sept 2025; est. 2028 to 2029.
601 Dover and Westcliff at Dover63 townhomes · Shea and D.R. HortonPlanning Commission approvals 2026; est. 2028 to 2029.
1300 Dove, Newport Beach132 homes · Lincoln PropertyApproved Aug 2026; est. 2029.
Westside live/work, Costa Mesa55 units across three projectsEntitled; est. 2027 to 2029.
Fairway Three, Newport Beach78 luxury homes · Eagle FourApproved Oct 2026; est. 2030 and later.
300 Newport Center150 high-rise condos · RelatedApproved Apr 2026; est. 2030 and later.
Get the pricing release first

One email when a community on this list opens its interest list or publishes pricing. Nothing else. Builders release to their own lists first, so being represented before the release matters more than it does on resale.

You can also email [email protected] or text (949) 995-5233.

Questions people ask

Newport Beach & Costa Mesa development, answered

Is Banning Ranch being developed?

No. The 387-acre site is now the Randall Preserve, purchased for permanent open space in 2022. Oil cleanup is underway and the earliest public opening is fall 2027, with the main entrance planned at West 17th Street in Costa Mesa.

What is Newport Beach Measure H?

A November 3, 2026 ballot measure that would cut the city's five housing focus areas from a combined 8,174-unit cap to 2,900 units, all income-restricted. Supporters say the city overzoned; opponents, including the state housing department, say passage could decertify the city's housing plan and trigger builder's-remedy projects and fines. Projects already on file keep today's rules.

Will the Fairview Developmental Center become housing?

Yes, eventually. Costa Mesa adopted a plan in September 2026 for up to 2,300 homes, 920 of them income-restricted, with 25 acres of open space on the 110-acre state campus at 2501 Harbor. The state still has to choose a master developer and fund roughly $300 million of site preparation, so construction is realistically years away.

Is One Metro West actually happening?

It is fully approved for 957 apartments and a 1.7-acre park at 1683 Sunflower, and the developer revised the plans as recently as May 2026, but it has not broken ground. The current target is first residents in 2028.

Is the Big Newport theater closing?

The Edwards family has said Regal's lease will not be extended past June 2027, and the site is approved for two 22-story condominium towers by Related California. The theater may close earlier. No construction schedule has been published.

Where can I buy new construction in Newport Beach or Costa Mesa right now?

Nowhere today, in the sense of a builder's sales office with released pricing. The first will be Meritage's Bear Street community in Costa Mesa, with models expected in 2027, followed by Intracorp's 1401 Quail condos in Newport Beach. The list above tracks every for-sale project in order.

What is Costa Mesa's Measure K rezoning?

Measure K, passed in 2022, let the city allow housing along Newport Boulevard, Harbor Boulevard, 17th, 18th, and 19th Streets, and everywhere north of the 405 without a public vote. The Neighborhoods Where We All Belong package heard by council in October 2026 writes the actual zoning: mostly 60-foot heights at 30 to 40 units per acre on the corridors and up to 108 feet on select North Costa Mesa sites.

How often is this page updated?

Quarterly, in January, April, July, and October, timed to the cities' annual housing reports and council calendars, plus any time a major project changes status. The date at the top is the last full review.

What does this mean for your street?

Every project on this page changes something for someone: a view, a commute, a school boundary, a resale comp. If you own or are buying near one of them, we will pull the current file, read the conditions of approval, and tell you plainly what to expect and when.

Project details are drawn from public city council and planning commission records, CEQA filings, California Coastal Commission reports, state housing department correspondence, and local press as of the date shown above. Status, unit counts, and timelines change; verify with the city before relying on them for a purchase, sale, or investment decision. Jade Larney is a licensed California real estate agent, not an attorney; nothing here is legal advice. Jade Vincent Larney, Anvil Real Estate, DRE 02241676. Brokered by Side, Inc., DRE 02014153. Equal Housing Opportunity.